Proposed Construction Staging Schedule

Stages 1 & 2 (Southview Boulevard to 7th Street)

  • REMOVALS (MID-APRIL TO LATE MAY)

  • UNDERGROUND UTILITY CONSTRUCTION (EARLY MAY TO MID JUNE)

  • ROAD AND SIDEWALK CONSTRUCTION (LATE MAY TO MID-JULY)

Stage 3 (7th Street to Park Street)

  • REMOVALS (EARLY AUGUST TO MID-AUGUST)

  • UNDERGROUND UTILITY CONSTRUCTION (MID-AUGUST TO EARLY SEPTEMBER)

  • ROAD AND SIDEWALK CONSTRUCTION (EARLY SEPTEMBER TO EARLY OCTOBER)

Stage 4 (Southview Boulevard to Park Street)

  • FINAL PAVING AND COMPLETION OF PROJECT (MID-OCTOBER TO LATE OCTOBER)