Proposed Project Schedule

  • Project Kick Off & Data Collection – October to December 2017

  • Public Open House 1 – January 30, 2018

  • Preliminary Design to 60% – January to September 2018

  • Public Open House 2 – October 10, 2018

  • Final Design & Permits – Fall and Winter 2018

  • Public Open House 3 – Spring 2019

  • Construction - 2019